Watch this video, and be ready to stop and rewind, as I did a number of times. This is one of the most beautifully done explanations of how a virtual power plant works that I have seen, built around a profile of Base Power, the Texas startup run by Zach Dell, (yes, son of that Michael Dell), which is pioneering the business model for home based batteries that can provide backup power for homeowners, while generating revenue for the company thru arbitrage of grid electric prices.
Texas is the natural place to jumpstart this company because of the deregulated nature of the grid. There are only 12 states where consumers have as much freedom to choose their electric supplier. One of them is Illinois,where Base has also established a presence.
In my state of Michigan, we are more tightly regulated, which has advantages and disadvantages, but has generally been slower to innovate. Nevertheless, we are now seeing a willingness to try a new approach, driven by burgeoning demand from onshoring manufacturing, electrification, and data centers. Utility DTE is collaborating with German based Sonnen in an Ann Arbor neighborhood.
DTE Energy and sonnen, a battery and virtual power plant technology provider, have launched Michigan’s first residential battery virtual power plant (VPP) pilot at Veridian at County Farm, a new carbon-neutral housing development in Ann Arbor.
VPPs use advanced software to connect and coordinate distributed energy resources (DERs)—everything from rooftop solar panels and home batteries to electric vehicles and smart appliances. They aggregate tens, hundreds or even thousands of connected DERs into a single, dispatchable resource, enabling VPPs to support the grid during peak demand, lower energy costs for consumers and delay or even eliminate the need for new grid infrastructure.
Thrive Collaborative, a local property developer focused on constructing life-enhancing communities, designed and built Veridian at County Farm as a virtual power plant. Each of its 170 fully electric homes include at least 1.3 MW of rooftop solar and a sonnen intelligent battery.
What Thrive Collaborative and sonnen didn’t have when they broke ground was DTE’s commitment to conduct the pilot project.
The developer “built the whole virtual power plant’s infrastructure with no DTE contract,” Blake Richetta, CEO of sonnen, told Microgrid Knowledge in an exclusive interview. Thrive’s founder Matt Grocoff had a “we will build it and they will come mentality,” Richetta added. “It was crazy risky for him.”

Approved by the Michigan Public Service Commission (MPSC), the two-year pilot will virtually connect nearly 100 homes through sonnen battery systems and VPP technology. By coordinating individual residential batteries as an additional grid resource, DTE will evaluate how this approach could ultimately help meet growing energy demand while supporting reliability and affordability goals for customers. This approach aligns with recent MPSC recommendations encouraging greater use of distributed energy resources and existing assets to help lower energy costs for Michigan families.
“Across Michigan, families are feeling the pressure of higher costs for groceries, housing, childcare and other everyday necessities, and we know affordability matters more than ever,” said Joi Harris, president and chief executive officer of DTE Energy. “That’s why we’re exploring innovative ways to make better use of energy resources. This pilot is an opportunity to test an approach that could ultimately provide a lower-cost way to meet growing energy needs and strengthen reliability. It’s exactly the kind of forward-thinking approach that has the potential to help keep energy affordable for customers over the long term.”
Through the pilot, DTE will evaluate how residential VPPs could ultimately help lower costs, support high demand periods and create new opportunities to deliver customer value. Insights from the pilot will help determine how residential virtual power plants could support a more affordable and clean energy future in Michigan.
DTE expects nearly 100 battery-equipped Veridian homes to ultimately participate in the pilot. So far, 44 market-rate homes with solar and batteries have been built, out of 120 planned, as have 50 affordable housing units that don’t have batteries yet, according to Thrive Collaborative. Battery manufacturer Sonnen USA, maker of the home storage systems installed at Veridian, is helping DTE operate the pilot using Sonnen’s proprietary software.
“Veridian is a test bed,” said Geoff Ferrell, executive vice president of Sonnen USA’s VPP business unit. The initiative, which is expected to be able to deliver up to about 300 kilowatts for three hours, will give DTE a clearer picture of how much power the home battery fleet can actually generate and when, providing “a really great basis” for a scaled-up program, he noted.